Western procurement teams ask the same questions before buying industrial equipment from China: who is the legal entity, what exactly is in scope, how acceptance is tested, and who stands behind the warranty. This page answers them in order.

Ten steps

From RFQ to warranty

  1. 01

    Send an RFQ

    Buyer · Day 0

    Drawing, resin system, target output, plant voltage, destination. The more complete, the faster the quotation.

  2. 02

    Engineering questions and DFM

    Factory engineering

    An engineer checks the profile and asks what is missing. You receive DFM notes on the cross-section and die concept.

  3. 03

    Quotation

    Shanghai export office

    Configuration, inclusions and exclusions, FAT criteria, payment milestones, Incoterm, lead time, manufacturer and warranty party, exporter of record.

  4. 04

    Factory audit (recommended)

    Buyer

    Visit Xinxiang, see the machines and dies running, meet the engineers. Third-party inspection by SGS, BV or TÜV is accepted at your cost.

  5. 05

    Contract and first payment

    Buyer + exporter

    Contract with the Shanghai exporter as seller; technical annex signed off by the factory. First milestone payment starts drawing and die design.

  6. 06

    Drawing approval

    Buyer

    You approve the layout and die 3D models before manufacture.

  7. 07

    FAT

    Factory + buyer

    The machine or line is run against the agreed pass/fail criteria, witnessed in person, by video or by your inspector.

  8. 08

    Shipment and documents

    Exporter of record

    Export customs, bill of lading, commercial invoice, packing list, certificate of origin. Incoterm per contract.

  9. 09

    Installation, SAT and training

    Factory engineers

    Supervised installation, site acceptance on your profile, operator training.

  10. 10

    Warranty and spare parts

    Manufacturer + exporter

    Warranty is provided by the manufacturer; the Shanghai office coordinates claims and parts shipments in English.

Parties

Two companies, clearly separated

ManufacturerHenan Zhongsheng Composite Material Co., Ltd., Muye District, Xinxiang, Henan, China. Builds the machines and dies; warranty party.
Seller and exporter of recordPultruded Export, Shanghai, China. Contracting party, export customs, shipping documents, after-sales coordination.
Contract languageEnglish. Technical annex in English with Chinese reference copy for the factory.
CurrencyUSD or EUR.
IncotermsFOB Chinese port by default; CIF or DAP on request.
InspectionSGS, BV, TÜV or your own inspector at FAT; cost borne by the buyer.
PaymentMilestones tied to contract, drawing approval, FAT acceptance and shipment. Split stated on each quotation.
Dispute resolutionStated in the contract.

Next step

Send a cross-section drawing. Get a DFM review and a scoped quotation.

Quotations state the manufacturer, the exporter of record, the warranty party, FAT scope and payment milestones. No figure is quoted without a drawing.